| The Supreme Court agreed with the Respondent’s
plea that the Appellants did not claim any set-off nor did they
file a counter-claim for the alleged amount due and payable
by the contractor on the alleged ground that Accountant-General’s
office had raised objection for payment of labour charges at
accelerated rate. As such the Arbitrator was right in not considering
the same which was sought to be raised after lapse of four years
of reference. Further the High Court has pointed out that the
learned Additional Advocate-General was unable to point out
any legal basis to support the contention that the Arbitrator
was required to go into the counter-claim in the circumstances
of the present case.
The Supreme Court also held that there is no substance in
the contention of the Appellant that the second reference
was barred by Order 2 Rule 2 of CPC. In any case, the dispute
with regard to the subsequent claims arose after the first
reference, that is, after the final bill was prepared and
this aspect was rightly dealt with by the Additional District
Judge.
The Supreme Court held that the Appellant did not raise the
contention before the District Court nor before the High Court
objecting to payment of interest on delayed payments to the
contractor under Clause 23 of the Agreement between the parties.
In view of the same, it cannot be held that the Arbitrator
committed any error apparent on the face of the record nor
did he commit any misconduct in passing the impugned award.
Since the objection with regard to payment of interest was
not raised before the Arbitrator or at any stage thereafter,
the Supreme Court held that it was not necessary for them
to deal with or decide the same in this appeal.
The Arbitrator granted interest on the principal amount of
claims at the rate of 18% p.a. and the District Court awarded
interest at the rate of 15% from the date of decree. However,
considering the dispute involved and overall circumstances
of the case the Supreme Court modified the award qua the rate
of interest and reduced the rate of interest to 6% per annum.
The SLP filed by the contractor for enhancement of interest
rate from 15% to 18% was dismissed.
|